posted on 2018-04-30, 13:38authored byPablo Ballesteros-Perez, Maria Luisa del Campo-Hitschfeld, Manuel Alejandro Gonzalez-Naranjo, M. Carmen Gonzalez-Cruz
Purpose: Construction projects usually suffer delays, and the causes of these delays and its cost overruns have been widely discussed, the weather being one of the most recurrent. The purpose of this paper is to analyze the influence of climate on standard construction work activities through a case study. Design/methodology/approach: By studying the extent at which some weather variables impede outdoor work from being effectively executed, new maps and tables for planning for delays are presented. In addition, a real case regarding the construction of several bridges in southern Chile is analyzed. Findings: Few studies have thoroughly addressed the influences of major climatic agents on the most common outdoor construction activities. The method detailed here provides a first approximation for construction planners to assess to what extent construction productivity will be influenced by the climate. Research limitations/implications: Although this study was performed in Chile, the simplified method proposed is entirely transferable to any other country, however, other weather or combinations of weather variables could be needed in other environments or countries. Practical implications: The implications will help reducing the negative social, economic and environmental outcomes that usually emerge from project delays. Originality/value: Climatic data were processed using extremely simple calculations to create a series of quantitative maps and tables that would be useful for any construction planner to decide the best moment of the year to start a project and, if possible, where to build it.
Funding
This research study was funded in Chile by CONICYT under the Programs Fondecyt de
Iniciación en investigación 2013 (project number 11130666) and FONDEF IDeA 2 etapas (project number ID14I10026).
History
School
Architecture, Building and Civil Engineering
Published in
Engineering, Construction and Architectural Management
Volume
22
Issue
6
Pages
596 - 621
Citation
BALLESTEROS-PEREZ, P. ...et al., 2015. Climate and construction delays: Case study in Chile. Engineering, Construction and Architectural Management, 22(6), pp. 596-621.
This work is made available according to the conditions of the Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International (CC BY-NC-ND 4.0) licence. Full details of this licence are available at: https://creativecommons.org/licenses/by-nc-nd/4.0/
Publication date
2015
Notes
This is an Open Access Article. It is published by Emerald under the Creative Commons Attribution 4.0 Unported Licence (CC BY). Full details of this licence are available at: http://creativecommons.org/licenses/by/4.0/