posted on 2014-06-26, 15:13authored byAnanda K.W. Jayawardane, Andrew Price, Francis C. Harris
In part A the authors describe the field data collection performed using Activity
Sampling and explain the principles of calculation, basic times, standard times,
placing times, operative factors, gang factors, site factors and balancing of gang
sizes. The research demonstrates that it is possible to obtain basic and standard times
for fairly complex operations and present these in the form of standard equations.
History
School
Architecture, Building and Civil Engineering
Citation
JAYAWARDANE, A.K.F., PRICE A.D.F. and HARRIS, F., 1995. Measurement of construction productivity: brickwork and blockwork. Part A. Building Research and Information, 23 (2), pp. 81 - 86.