Existing literature and research findings indicated that delays are common amongst
construction projects in many countries across the globe. Delays can be caused by
one or more of the following: the client (excusable with compensation); force majeur
or third party (excusable delays without compensation); or the contractors (non-excusable
delays or contractor-responsible delays). Previous studies cited that
approximately 50% of these delays can be classified as non-excusable delays. The
root-causes (or factors) that cause non-excusable delays identified in these studies
however, are given no detailed attention. Improving and constantly monitoring the
factors causing non-excusable delays can help to determine and improve contractor's
performance.
This research explores issues related to the factors causing non-excusable delays. [Continues.]
This work is made available according to the conditions of the Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International (CC BY-NC-ND 4.0) licence. Full details of this licence are available at: https://creativecommons.org/licenses/by-nc-nd/4.0/
Publication date
1997
Notes
A Doctoral Thesis. Submitted in partial fulfilment of the requirements for the award of Doctor of Philosophy at Loughborough University.